SW Ring Road Work Set To Begin

Update September 15 2016: A $1.42 billion contract (adjusted to 2016 dollars) has been signed between the Province of Alberta and Mountain View Partners for the construction of the Southwest Calgary Ring Road project. Click here for details.


 

Mountain View Partners have been selected to begin initial work on the Southwest Calgary Ring Road project under an interim agreement. While the full contract will not be entered into until September 13, this interim agreement will allow work to begin along the road corridor, including the relocation of utilities. The Alberta Government expects to see crews and equipment on the project site by mid-July.

Mountain View Partners is a consortium consisting of:

  • Project Lead:  Meridiam Infrastructure North America Fund II, as managed by Meridiam Infrastructure North America Corp.
  • Financing Lead:  Meridiam Infrastructure North America Fund II, as managed by Meridiam Infrastructure North America Corp.
  • Design-Construction Lead:  Kiewit Management Co.
  • Operation and Maintenance Lead:  Alberta Highway Services Ltd.

 

Click Here for maps of the full Southwest Calgary Ring Road Project.


Source: “Southwest Calgary Ring Road construction begins” July 8 2016. Government of Alberta.

2015 Southwest Calgary Ring Road Maps

The following maps were released to the public in October of 2015 by the Province of Alberta, and rather than relying on older or historical maps of the project, I wanted to ensure that the most up-to-date information was available to readers. These are likely to remain the most current views of the road until a contractor is selected in September of this year.

Please click on the maps for larger versions.

Southwest Calgary Ring Road Route

From North to South, the following maps show the full route of the Southwest Calgary Ring Road project as it currently stands:

1) While not part of the Southwest Calgary Ring Road, Highway 8 from Lott Creek Boulevard to the Calgary City Limits at 101st Street SW will be twinned as part of the project, including a new bridge over the Elbow river.

01-SW-CRR-Highway_8


2) The Southwest Ring Road begins at the Highway 8 Corridor, from Calgary City Limits at 101st Street SW, to the interchange at 69th Street SW.

02-SW-CRR-69th_Street_SW


3) Interchange of Glenmore Trail SW and Sarcee Trail SW, including Glenmore Trail upgrades between Sarcee Trail SW and the 37th Street SW interchange. Also shown are the interchanges with Westhills Way SW and Strathcona Street.

SW-CRR - Sarcee Tr SW / Glenmore Tr SW / 37 Street SW / Westhill Continue reading “2015 Southwest Calgary Ring Road Maps”

Federal Funding Announcement

On Thursday July 30 2015, Federal Minister for National Defence and Multiculturalism Jason Kenney, along with Alberta Minister for Transportation Brian Mason, announced Federal funding for the Southwest Calgary Ring Road project.

At the announcement, also attended by Tsuut’ina Chief Roy Whitney-Onespot, Kenney detailed a commitment of $582.9 million, which represents one quarter of the estimated $2.8 billion cost for construction of this leg of the road. The funds are being earmarked from the National Infrastructure Component of the New Building Canada Fund, which ‘provides funding for projects of national significance’1.

July_2015_update_new

(Map showing the newly revised route of the Southwest ring road; from Macleod trail in the south, to west of 101st street SW in the west.)

Continue reading “Federal Funding Announcement”

Highway 8 and the Ring Road

This month, the Government of Alberta revised the plans for the Southwest Calgary Ring Road Project by extending the western portion of the road into the Highway 8 corridor. This section of the ring road, what is currently Highway 8 from Sarcee trail to just west of the Calgary city limits and highlighted below in blue, had until recently been a part of the West Calgary Ring Road Project. This change shifts approximately 5km of roadway to the Southwest ring road, adds one additional interchange (69th street SW) and a new crossing over the Elbow River to the project, while removing the same from the West leg of the road.1

July_2015_update_new(The previous Southwest ring road route in green, with the addition of a portion of Highway 8 in blue, making up the most recent Southwest ring road alignment.2)

This section of Highway 8, between Sarcee trail and 101st street, has played an important role in the history of the ring road, not only recently, but for many years before.

South Morley Trail, Springbank Trail, Richmond Road and Highway 8

The modern Highway 8 partially follows the route of one of the oldest roads on Calgary’s west side. Richmond road, first known as South Morley Trail, was a key trail west of the city in the 19th century, and originally connected Calgary to the Stoney Nakoda First Nation Reserve via Springbank.3

1894_Richmond_Road(The Richmond road corridor highlighted in pink, 1894.3)
Continue reading “Highway 8 and the Ring Road”

Budget 2015 and the Ring Road

Yesterday the Alberta government announced details of the proposed budget for 2015, which includes information about the two remaining portions of the Calgary Ring Road. As a cost-cutting measure, the West Calgary Ring Road is being delayed by four years, and construction is now slated to begin in 2020/2021. Expected completion of this leg, and ultimately the entire ring road, will not occur until 2024/2025, and the measure is expected to defer a reported $1.5 billion from the current budget time-frame. W&SW_Ring_Road The Southwest Calgary Ring Road, the portion that runs through the Tsuut’ina Nation reserve, remains unaffected. Work will begin on this leg of the road once the Tsuut’ina land transfer has been approved and once a contract has been tendered and awarded, with construction expected to begin next year. The agreement signed between the Nation and the Province in 2013 commits the Province to open the Southwest portion of the road within 7 years of the land transfer, and the opening is estimated to occur in 2020. The 2015 budget allocates $2.9 billion over the next 5 years towards the construction of Alberta’s ring roads. This figure includes funds needed to complete Edmonton’s Anthony Henday Drive as well as beginning work on the Southwest Calgary Ring Road (interestingly referred to as ‘Southwest Stoney Trail’ in the Province’s 5-year Capital Plan despite a promised name change as the road crosses through former Tsuut’ina reserve lands).

Storm Trunk Relocation: The first steps to the SW Ring Road

In June of 2015, the City of Calgary will begin to construct some of the first tangible work on the Southwest Calgary Ring Road Project. This work will not be on the road itself, but will be related to utilities that will run under part of the project.

The City and Province of Alberta has agreed to construct a new storm sewer line to replace the existing South Richmond Storm Trunk that currently crosses a portion of the Tsuut’ina Nation reserve known as ‘the 940‘. The new line will be located entirely within the City of Calgary city limits along 37th street SW in Lakeview when completed, while the old line will be abandoned. This abandonment and replacement is not due to the functionality or suitability of the existing infrastructure, rather it is necessary due to reasons that are political and jurisdictional in nature; reasons that go back more than 60 years.

stormtrunk_b

Continue reading “Storm Trunk Relocation: The first steps to the SW Ring Road”

SW Ring Road Information Sessions Announced

Alberta Transportation has announced the dates and locations for their upcoming information sessions, covering the West and Southwest Calgary Ring Road projects.

W&SW_Ring_Road Continue reading “SW Ring Road Information Sessions Announced”